61. In
_______ estimation method component tasks are identified and sized and these
individual estimates
are
aggregated
A. top-down
B. bottom up.
C. procedural oriented
D. algorithmic model.
ANSWER: B
62. In
prototyping, the extent to which the copies of input screen are shown to the
users on the
workstation,
but screens cannot actually be used is _____ .
A. simulated interaction
B. partial working model
C. vertical working model.
D. mock-ups.
ANSWER: D
63. The
______ event is constructed and tested quickly and inexpensively in order to
test the assumptions.
A. data flow diagrams
B. UML diagrams
C. prototype.
D. product based structure.
ANSWER: C
64. The
V-process model deals with expanding the activity _____.
A. tasks.
B. efforts
C. testing.
D. process.
ANSWER: D
65. The
critical path is the ________ path through the network
A. shortest.
B. nearest.
C. path with interference float.
D. longest.
ANSWER: C
66. The
_______ risks affect the organisation developing or procuring the software.
A. product
B. process.
C. business
D. project.
ANSWER: C
67. The
_____i option is used to find the approach of the identification of risks.
A. milestone.
B. brainstorming.
C. risk planning
D. risk monitoring
ANSWER: B
68. ._____
is one of the ways of identifying possible threats to the success of a project
and the measures
that might
eliminate or reduce them.
A. Causal mapping
B. Checklists.
C. Brainstorming.
D. Risk assessment
ANSWER: A
69.
.________ is a planned action to be carried out if the particular risk
materializes.
A. Contingency plan
B. Risk transfer
C. Integration plan.
D. Risk mitigation
ANSWER: A
70. Risk __________is
a action taken to ensure that the impact of the risk is lessened when it occurs
A. reduction.
B. avoidance.
C. mitigation
D. planning.
ANSWER: C