SOFTWARE PROJECT MANAGEMENT - Multiple Choice Questions. 005

41. The _______will be of concern at all stages of project planning and execution, but will be of particular
interest at the some points of stepwise frame work.
 A. software coding
 B. software testing.
 C. software quality
 D. software verification
 ANSWER: C
42. The _______makes it difficult to know that a particular task in a project has been completed
satisfactorily.
 A. increasing criticality of software
 B. accumulating errors during software development
 C. intangibility of software.
 D. decreasing criticality of software
 ANSWER: C
43. In quality specification, ______is the range of values within which it is planned the quality
measurement value should lie.
 A. now.
 B. minimally acceptable
 C. target range.
 D. scale.
 ANSWER: C
44. The ______is the extent to which a program satisfies its specifications and fulfills the users objectives.
 A. correctness
 B. efficiency
 C. integrity.
 D. usability.
 ANSWER: B
45. The ______describes the fundamental features of quality management system (QMS) and the
terminology used.
 A. ISO 9000.
 B. ISO 9001.
 C. ISO 9001-2000
 D. ISO 9001-2001.
 ANSWER: A
46. CMM stands for _______.
 A. component maturity models
 B. capability maturity models
 C. common maturity models.
 D. comfort maturity models
 ANSWER: B
47. The UK government has sponsored PRINCE2 procedures through _____.
 A. office of government commerce
 B. office of government companies
 C. office of general companies.
 D. office of general commerce
 ANSWER: A
48. The _______have a good fit with SSADM
 A. OOAD.
 B. PRINCE.
 C. PROMPT.
 D. Waterfall model.
 ANSWER: B
49. PRINCE2 is ______ based project for handling many a task.
 A. activity.
 B. task.
 C. product.
 D. process.
 ANSWER: C
50. In PRINCE2, the task of managing the project on a day-to-day basis will be delegated to _____.
 A. team manager.
 B. project steering committee
 C. team member.
 D. project manager.


 ANSWER: D